Marymount University Project Cost Management Data Analysis The questions are the 12 questions: 1. Using our understanding of “Project Cost Management” Dat

Marymount University Project Cost Management Data Analysis The questions are the 12 questions:

1. Using our understanding of “Project Cost Management” Data Analysis, select the ONE CORRECT description of the following phrase:
This is the total cost incurred in accomplishing the work.

Don't use plagiarized sources. Get Your Custom Essay on
Marymount University Project Cost Management Data Analysis The questions are the 12 questions: 1. Using our understanding of “Project Cost Management” Dat
Get an essay WRITTEN FOR YOU, Plagiarism free, and by an EXPERT!
Order Essay

A) Earned Value Management (EVM)

B) Earned Value (EV)

C) Earned Value (EV)

D)Actual Cost (AC)

2. Looking at Figure 7-12 in the textbook and using the “Data Date” that they have indicated with the vertical line, select the ONE CORRECT answer regarding the example project SCHEDULE.

A) The earned value has caused the project to be ahead of schedule at this point.

B) The SPI cannot be calculated for this example since there are no numbers to conduct the mathematical problem.

C) The project will absolutely over run the total schedule if the current burn rate continues.

D) The project will absolutely under run the total schedule [e.g. come in ahead of schedule] if the current burn rate continues.

E) If you could calculate the SPI value, it would indicate that at that particular moment in time, the project is behind schedule.

3. Using our understanding of “Project Cost Management”, select the ONE CORRECT description of the following phrase: This is the process of aggregating the estimated costs of individual activities to establish a cost baseline.

Estimate Costs
Control Budget
Control Costs
Determine Costs
Plan Cost Management
Control Estimates
Determine Budget

4. Using our understanding of “Project Cost Management” Data Analysis, select the ONE CORRECT description of the following phrase: This is the budget associated with the work that has been completed.

Earned Value (EV)
Earned Value Management (EVM)
Actual Cost (AC)
Planned Value (PV)

5. Using our understanding of “Project Cost Management”, select the ONE CORRECT description of the following phrase: This is the process of developing an approximation of the money needed to complete the project work.

Determine Budget
Control Costs
Estimate Costs
Control Estimates
Determine Costs
Plan Cost Management
Control Budget

6. Using our understanding of “Project Cost Management”, select the ONE CORRECT description of the following phrase: This is the process of defining how the project costs will be estimated, budgeted, managed, monitored, and controlled.

Plan Cost Management
Determine Costs
Control Budget
Estimate Costs
Control Costs
Determine Budget
Control Estimates

7. Using our understanding of “Project Cost Management”, select the ONE CORRECT description of the following phrase: This is the MOST important task within the “Project Cost Management” activities.

Control Costs
Determine Budget
Determine Costs
Estimate Costs
Control Estimates
Plan Cost Management
Control Budget

8. Looking at Figure 7-12 in the textbook and assuming the “Data Date” (vertical) line represents “Today’s Date”, select the ONE CORRECT answer regarding the example project COST.

The project will absolutely under run the total costs if the current burn rate continues.
If you could calculate the CPI value, it would indicate that at that particular moment in time, the project indicates a cost overrun.
The earned value has caused the project to be under-budget at this point.
The project will absolutely over run the total costs if the current burn rate continues.
The CPI value cannot be calculated for this example since there are no numbers to conduct the mathematical problem.
Using our understanding of “Project Cost Management”, select the ONE CORRECT description of the following phrase:

9. This is the ONLY “Project Cost Management” activity that has ONLY ONE output.

Estimate Costs
Determine Budget
Control Costs
Plan Cost Management
Control Budget
Control Estimates
Determine Costs

10. Looking at Figure 7-12 in the text, identify the ONE CORRECT answer listed here.

As of this point in time, this is NOT a successful project from a financial perspective.
The total health of this project cannot be determined since we do not know if we met the project schedule.
The project that this diagram represents never went over budget during the course of the project.
This was a successful project from a financial perspective.Using our understanding of “Project Cost Management”, select the ONE CORRECT description of the following phrase:

11. This is the ONLY “Project Cost Management” activity that is NOT performed during the “Planning Process.”

Control Estimates
Control Costs
Estimate Costs
Control Budget
Determine Budget
Plan Cost Management
Determine Costs

12. Using our understanding of “Project Cost Management” Data Analysis, select the ONE CORRECT description of the following phrase: This is the budget planned for the work to be accomplished.

Planned Value (PV)
Earned Value Management (EVM)
Earned Value (EV)
Actual Cost (AC)

Calculate your paper price
Pages (550 words)
Approximate price: -

Why Choose Us

Top quality papers

We always make sure that writers follow all your instructions precisely. You can choose your academic level: high school, college/university or professional, and we will assign a writer who has a respective degree.

Professional academic writers

We have hired a team of professional writers experienced in academic and business writing. Most of them are native speakers and PhD holders able to take care of any assignment you need help with.

Free revisions

If you feel that we missed something, send the order for a free revision. You will have 10 days to send the order for revision after you receive the final paper. You can either do it on your own after signing in to your personal account or by contacting our support.

On-time delivery

All papers are always delivered on time. In case we need more time to master your paper, we may contact you regarding the deadline extension. In case you cannot provide us with more time, a 100% refund is guaranteed.

Original & confidential

We use several checkers to make sure that all papers you receive are plagiarism-free. Our editors carefully go through all in-text citations. We also promise full confidentiality in all our services.

24/7 Customer Support

Our support agents are available 24 hours a day 7 days a week and committed to providing you with the best customer experience. Get in touch whenever you need any assistance.

Try it now!

Calculate the price of your order

Total price:
$0.00

How it works?

Follow these simple steps to get your paper done

Place your order

Fill in the order form and provide all details of your assignment.

Proceed with the payment

Choose the payment system that suits you most.

Receive the final file

Once your paper is ready, we will email it to you.

Our Services

No need to work on your paper at night. Sleep tight, we will cover your back. We offer all kinds of writing services.

Essays

Essay Writing Service

You are welcome to choose your academic level and the type of your paper. Our academic experts will gladly help you with essays, case studies, research papers and other assignments.

Admissions

Admission help & business writing

You can be positive that we will be here 24/7 to help you get accepted to the Master’s program at the TOP-universities or help you get a well-paid position.

Reviews

Editing your paper

Our academic writers and editors will help you submit a well-structured and organized paper just on time. We will ensure that your final paper is of the highest quality and absolutely free of mistakes.

Reviews

Revising your paper

Our academic writers and editors will help you with unlimited number of revisions in case you need any customization of your academic papers