Q1) 10,000 gallons per day of wastewater enters a 1500 gallon activated sludge tank.  The raw wastewater has a SS = 200 ppm and a BOD = 230 ppm.  The MLSS needs to be 2800 ppm and the effluent SS should be less than 10 ppm.  The total wasted sludge has a Q of 5 GPD with a SS concentration of 6000 ppm.

  1. Calculate the recycle flow, Qr, required. (8710 GPD)
  2. Calculate the F/M ratio in lbs BOD/lbs SS – day (0.55  lb BOD/lb SS-day)
  3. Calculate the BOD Loading in lbs BOD/day – 1000 ft3(95.6)

 

Don't use plagiarized sources. Get Your Custom Essay on
Environmental Engineering | Homework Helpers
Get an essay WRITTEN FOR YOU, Plagiarism free, and by an EXPERT!
Order Essay
  1. Based on these calculations, is the activated sludge tank over designed or under designed?  What could you do to remedy this situation?

 

Q2)   Colloidal gold has been released into the water supply from an electronics manufacturing plant.  These particles are 0.1 mm in size with a specific gravity of 19.3.  Your water treatment plant has 3 clarifiers each with a volume of 0.3 million gallons and a height of 6 ft. The total flow going into all 3 clarifiers is 5 MGD.

 

 

 

 

 

  1. Will these particles settle in this clarifier or will we be drinking gold? Assume that they are not flocculated.  Defend your answer quantitatively.

 

  1. What is the minimum detention time needed to settle these gold particles over a height of 6 ft? (214 days)

 

  1. If you cannot remove these gold particles, should you aID a sand filter or a reverse osmosis unit?  Give two reasons for your answer and state your assumptions.

 

  1. If you decide to flocculate these particles, what is the minimum diameter of a gold particle (with a specific gravity of 19.3) that can be removed in this clarifier? (3.4 mm)

 

Q3)  You are given the following information:

 

 

 

 

 

  Conc,

mg/L

MW

g/mole

EW

mg/meq

Conc,

meq/L

Conc

mg/L as CaCO3

Ca2+ 180 40      
Mg2+   24.3     173
Na+ 30 23      
CO32–   60     169
HCO3– 8 61      
SO42- 11 96      
OH–   17      

 

  1. Calculate the hardness in meq/L. (12.5 meq/L)

 

Q4)     An activated sludge tank treats 1 MGD from the primary clarifier and has an [SS], or X of 2200 ppm. The water effluent is 0.9 MGD. 1.0 MGD of the sludge is recycled back into the tank and has an [SS] of 3980 ppm. The concentration of BOD exiting the primary clarifier is 200 ppm.a.     Calculate the minimum volume of the tank that will satisfy the following requirements:  (Hint:  Calculate the volume for each condition and then determine which volume satisfied all the requirements).

 

 

 

 

 

  1. BOD loading < 35 lb BOD/1000 ft3– day

&nbsp;

  1. Sludge age > 5 days

&nbsp;

iii. Aeration period > 4 hours

&nbsp;

Q5)&nbsp; &nbsp;&nbsp;10,000 gallons per day of wastewater enters a 1500 gallon activated sludge tank.&nbsp; The raw wastewater has a SS = 200 ppm and a BOD = 230 ppm.&nbsp; The MLSS needs to be 2800 ppm and the effluent SS should be less than 10 ppm.&nbsp; The total wasted sludge has a Q of 5 GPD with a SS concentration of 6000 ppm.

&nbsp;

&nbsp;

&nbsp;

&nbsp;

&nbsp;

  1. Calculate the recycle flow, Qr, required. (8710 GPD)

&nbsp;

  1. Calculate the F/M ratio in lbs BOD/lbs SS – day (0.55&nbsp;&nbsp;lb BOD/lb SS-day)

&nbsp;

  1. Calculate the BOD Loading in lbs BOD/day – 1000 ft3(95.6)

Based on these calculations, is the activated sludge tank over designed or under designed?&nbsp; What could you do to remedy this situation

&nbsp;

Q6) &nbsp;Water flows out of the primary clarifier with a SS = 200 ppm and a BOD = 250 ppm.&nbsp; An activated sludge tank treats 5 MGD from the primary clarifier and has an [SS], or X of 2500 ppm. The water effluent is 95% of the influent and 50% of the sludge is recycled back into the activated sludge tank with an [SS] of 6800 ppm.&nbsp; What is Qe? in MGD

&nbsp;

Q7) &nbsp;&nbsp;Water flows out of the primary clarifier with a SS = 200 ppm and a BOD = 250 ppm.&nbsp; An activated sludge tank treats 5 MGD from the primary clarifier and has an [SS], or X of 2500 ppm. The water effluent is 95% of the influent and 50% of the sludge is recycled back into the activated sludge tank with an [SS] of 6800 ppm.&nbsp; What is Qr? in MGD

&nbsp;

Q8) &nbsp;Water flows out of the primary clarifier with a SS = 200 ppm and a BOD = 250 ppm.&nbsp; An activated sludge tank treats 5 MGD from the primary clarifier and has an [SS], or X of 2500 ppm. The water effluent is 95% of the influent and 50% of the sludge is recycled back into the activated sludge tank with an [SS] of 6800 ppm.&nbsp; What is Qc&nbsp;(the flow leaving the bottom of the secondary clarifier)? in MGD

&nbsp;

Q9)&nbsp;Water flows out of the primary clarifier with a SS = 200 ppm and a BOD = 250 ppm.&nbsp; An activated sludge tank treats 5 MGD from the primary clarifier and has an [SS], or X of 2500 ppm. The water effluent is 95% of the influent and 50% of the sludge is recycled back into the activated sludge tank with an [SS] of 6800 ppm.&nbsp; What is Xw? in ppm

&nbsp;

Q10)The BOD loading you calculate is 53 lb BOD/1000 ft3-day. The BOD loading should be between 30 – 50 lb BOD/1000 ft3-day.&nbsp; Is the tank over or under designed?

under designed
over designed
It is just fine

&nbsp;

&nbsp;

Q11)BOD in wastewater can be represented in all the following ways EXCEPT:

SS
BOD
S
F

&nbsp;

&nbsp;

Q12)n an activated sludge tank it is best if the microorganisms have:

less food than they need so that all the food is gone.
more food than they need so that the microorganisms continue to reproduce.
no food so they all die.


Calculate your paper price
Pages (550 words)
Approximate price: -

Why Choose Us

Top quality papers

We always make sure that writers follow all your instructions precisely. You can choose your academic level: high school, college/university or professional, and we will assign a writer who has a respective degree.

Professional academic writers

We have hired a team of professional writers experienced in academic and business writing. Most of them are native speakers and PhD holders able to take care of any assignment you need help with.

Free revisions

If you feel that we missed something, send the order for a free revision. You will have 10 days to send the order for revision after you receive the final paper. You can either do it on your own after signing in to your personal account or by contacting our support.

On-time delivery

All papers are always delivered on time. In case we need more time to master your paper, we may contact you regarding the deadline extension. In case you cannot provide us with more time, a 100% refund is guaranteed.

Original & confidential

We use several checkers to make sure that all papers you receive are plagiarism-free. Our editors carefully go through all in-text citations. We also promise full confidentiality in all our services.

24/7 Customer Support

Our support agents are available 24 hours a day 7 days a week and committed to providing you with the best customer experience. Get in touch whenever you need any assistance.

Try it now!

Calculate the price of your order

Total price:
$0.00

How it works?

Follow these simple steps to get your paper done

Place your order

Fill in the order form and provide all details of your assignment.

Proceed with the payment

Choose the payment system that suits you most.

Receive the final file

Once your paper is ready, we will email it to you.

Our Services

No need to work on your paper at night. Sleep tight, we will cover your back. We offer all kinds of writing services.

Essays

Essay Writing Service

You are welcome to choose your academic level and the type of your paper. Our academic experts will gladly help you with essays, case studies, research papers and other assignments.

Admissions

Admission help & business writing

You can be positive that we will be here 24/7 to help you get accepted to the Master’s program at the TOP-universities or help you get a well-paid position.

Reviews

Editing your paper

Our academic writers and editors will help you submit a well-structured and organized paper just on time. We will ensure that your final paper is of the highest quality and absolutely free of mistakes.

Reviews

Revising your paper

Our academic writers and editors will help you with unlimited number of revisions in case you need any customization of your academic papers